NEW KITCHEN CONSTRUCTION PROGRESS

Construction by;
Jon Hollway
Corbett Creek Contracting
Jonathan.hollway@gmail.com
807 356 3523

SEP 10, 2026 Further Work on Sheeting.

SEP 30, 2026 Tyvek Covering.

OCT 02, 2026 Windows Installed.

OCT 10, 2026 Door and Stairs.


AUG 05, 2026 Construction has begun.
Today the site was cleared and levelled.


AUG 06, 2026 Foundation work begins.
Placement of sono tubes.


AUG 07, 2026 Sono tubes all in place.


AUG 12, 2026 Cement Poured.


AUG 13, 2026 Framing Begins.


AUG 14, 2026 Base Structure.


AUG 17, 2026 Laying out the Walls.


AUG 25, 2026 Raising the Walls.


AUG 26, 2026 Framework Complete.


AUG 27, 2026 Roof and Walls Sheeted.